Construction Status Tracker – Nambiar District 25
Buying into a large integrated township like Nambiar District 25 (D25) is a long-term decision. For most buyers, the biggest concern isn’t just brochures or model apartments — it’s whether construction is actually happening on schedule. This page is your transparent, month-by-month construction tracker, based on official RERA schedules, on-site photos, and verified progress reports.
Quick Snapshot — Construction Progress Table
| Month / Year |
Activity |
Notes |
| Jan 31, 2025 |
Phase 1 – Excavation initiated |
Verified via official builder site |
| Feb 25, 2025 |
Excavation in progress |
Phase-1 bulk excavation continuing |
| Apr 2025 |
Tower 1 & 2 excavation in progress |
Simultaneous works across towers |
| Apr 2025 |
Tower 3 – Raft concreting works in progress |
First major structural activity |
| May 2025 |
Excavation in progress |
Final phases of excavation nearing close |
This table will be updated every month with verified milestones.
Nambiar District 25 Construction Photos
Jan 31, 2025 - Phase 1 – Excavation initiated
Feb 25, 2025 - Excavation in progress
Apr 2025 - Tower 1 & 2 excavation in progress
Apr 2025 - Tower 3 – Raft concreting works in progress
May 2025 - Excavation in progress
Detailed Month-by-Month Timeline
January 2025 – Breaking Ground
- Phase 1 officially began with excavation initiation on Jan 31, 2025.
- This is the first milestone in the sub-structure schedule as per RERA (earthwork & leveling Jan–Jun 2025).
February 2025 – Excavation Continues
- On Feb 25, 2025, excavation was visibly progressing on multiple blocks.
- This aligns with the RERA timeline: Earthwork expected until mid-June 2025.
April 2025 – Major Structural Kick-off
- Towers 1 & 2: Excavation still in progress.
- Tower 3: Raft concreting works began — the first visible reinforced concrete activity.
- According to RERA, foundation footing work is scheduled Apr–Oct 2025 — perfectly matching the on-ground activity.
May 2025 – Sub-Structure Advancing
- Excavation still active, but nearing completion on multiple blocks.
- This paves the way for foundation and plinth works scheduled to run into early 2026.
RERA-Linked Project Schedule Highlights
Phase 1 (Contractor: Nambiar Inhouse)
- Sub-Structure: Jan 2025 – May 2026 (excavation, footing, plinth, parking, retaining wall).
- Super-Structure: Nov 2025 – Nov 2027 (RCC framing, masonry, plastering, joinery, tiling).
- Finishing Works: Aug 2026 – Oct 2029 (painting, electrification, fire safety, weather-proofing, landscaping).
- Target possession window: Dec 2028 – Jan 2030 (depending on tower/phase).
Phase 2 (Contractor: Kalpataru Projects Intl.)
- Sub-Structure: Sep 2025 – Jul 2027.
- Super-Structure: Jun 2026 – Sep 2028.
- Finishing Works: Jan 2027 – Feb 2030.
- Target possession window: Late 2029 – 2030.
FAQs (SEO + Schema-ready)
As of May 2025, Phase 1 excavation is nearing completion, with raft concreting already underway for Tower 3.
Phase 1 has a possession date is February 01, 2030. Phase 2 has a possession date of September 05, 2023.
- Phase 1: In-house Nambiar execution led by Architect Gnanavel Thirumaran and Engineer Ramesh B.
- Phase 2: Executed by Kalpataru Projects International Ltd., with the same architectural oversight.
- 3 BHK – 1600 sq. ft, starts from Rs. 1.60 crores
- 4 BHK – 2700 sq. ft, starts from Rs. 2.70 crores
Why This Tracker Matters
Most listings only show glossy brochures. Here, you’re getting real, timestamped construction updates you can rely on — aligned with RERA filings. Bookmark this tracker and check back monthly for the latest verified progress.