Construction Status Tracker – Nambiar District 25

Construction Status Tracker – Nambiar District 25


Construction Status Tracker of Nambiar District 25 showcasing latest project updates and progress

Buying into a large integrated township like Nambiar District 25 (D25) is a long-term decision. For most buyers, the biggest concern isn’t just brochures or model apartments — it’s whether construction is actually happening on schedule. This page is your transparent, month-by-month construction tracker, based on official RERA schedules, on-site photos, and verified progress reports.

Quick Snapshot — Construction Progress Table

Month / Year Activity Notes
Jan 31, 2025 Phase 1 – Excavation initiated Verified via official builder site
Feb 25, 2025 Excavation in progress Phase-1 bulk excavation continuing
Apr 2025 Tower 1 & 2 excavation in progress Simultaneous works across towers
Apr 2025 Tower 3 – Raft concreting works in progress First major structural activity
May 2025 Excavation in progress Final phases of excavation nearing close

This table will be updated every month with verified milestones.

Nambiar District 25 Construction Photos

Phase 1 – Excavation initiated

Jan 31, 2025 - Phase 1 – Excavation initiated

Excavation in progress

Feb 25, 2025 - Excavation in progress

Tower 1 & 2 excavation in progress

Apr 2025 - Tower 1 & 2 excavation in progress



Tower 3 – Raft concreting works in progress

Apr 2025 - Tower 3 – Raft concreting works in progress

May 2025 - Excavation in progress

May 2025 - Excavation in progress


Detailed Month-by-Month Timeline

January 2025 – Breaking Ground

  • Phase 1 officially began with excavation initiation on Jan 31, 2025.
  • This is the first milestone in the sub-structure schedule as per RERA (earthwork & leveling Jan–Jun 2025).

February 2025 – Excavation Continues

  • On Feb 25, 2025, excavation was visibly progressing on multiple blocks.
  • This aligns with the RERA timeline: Earthwork expected until mid-June 2025.

April 2025 – Major Structural Kick-off

  • Towers 1 & 2: Excavation still in progress.
  • Tower 3: Raft concreting works began — the first visible reinforced concrete activity.
  • According to RERA, foundation footing work is scheduled Apr–Oct 2025 — perfectly matching the on-ground activity.

May 2025 – Sub-Structure Advancing

  • Excavation still active, but nearing completion on multiple blocks.
  • This paves the way for foundation and plinth works scheduled to run into early 2026.

RERA-Linked Project Schedule Highlights

Phase 1 (Contractor: Nambiar Inhouse)

  • Sub-Structure: Jan 2025 – May 2026 (excavation, footing, plinth, parking, retaining wall).
  • Super-Structure: Nov 2025 – Nov 2027 (RCC framing, masonry, plastering, joinery, tiling).
  • Finishing Works: Aug 2026 – Oct 2029 (painting, electrification, fire safety, weather-proofing, landscaping).
  • Target possession window: Dec 2028 – Jan 2030 (depending on tower/phase).

Phase 2 (Contractor: Kalpataru Projects Intl.)

  • Sub-Structure: Sep 2025 – Jul 2027.
  • Super-Structure: Jun 2026 – Sep 2028.
  • Finishing Works: Jan 2027 – Feb 2030.
  • Target possession window: Late 2029 – 2030.

FAQs (SEO + Schema-ready)

As of May 2025, Phase 1 excavation is nearing completion, with raft concreting already underway for Tower 3.

Phase 1 has a possession date is February 01, 2030. Phase 2 has a possession date of September 05, 2023.

  • Phase 1: In-house Nambiar execution led by Architect Gnanavel Thirumaran and Engineer Ramesh B.
  • Phase 2: Executed by Kalpataru Projects International Ltd., with the same architectural oversight.
  • 3 BHK – 1600 sq. ft, starts from Rs. 1.60 crores
  • 4 BHK – 2700 sq. ft, starts from Rs. 2.70 crores

Why This Tracker Matters

Most listings only show glossy brochures. Here, you’re getting real, timestamped construction updates you can rely on — aligned with RERA filings. Bookmark this tracker and check back monthly for the latest verified progress.

×